Lifetime extension of Rivne Nuclear Power Plant |
SUMMARY |
At its twenty-first session (20 June 2011), the Committee began its consideration of the information provided by a Ukrainian non-governmental organization regarding the planned extension of the Rivne nuclear power plant (NPP) in Ukraine, close to the border with Belarus and Poland (EIA/IC/INFO/7). |
It asked the Chair to invite the Government of Ukraine to provide information on the environmental impact assessment (EIA) for the planned activity, as well as clarification on whether the Government had taken the necessary legal, administrative and other measures to implement the provisions of the Convention. |
The Committee further considered the information received at its twenty-second (5-7 September 2011), twenty-third (5-7 December 2011), and twenty-fifth (11-13 September 2012) sessions. At its twenty-seventh session (12-14 March 2013), the Committee decided to begin a Committee initiative further to paragraph 6 of the Committee's structure and functions. |
In line with paragraph 9 of the Committee's structure and functions, the Committee decided to invite Ukraine to its twenty-eighth session (10-12 September 2013) to participate in the discussion and to present information and opinions on the matter under consideration. |
The Committee adopted its findings and recommendations on its thirtieth session (25-27 February 2014) and requested the secretariat to transmit them for consideration by the MOP at its sixth session (2-5 June 2014). The MOP considered the Committee's findings and recommendations, as reflected in decision VI/2. For the outcomes of the Committee’s deliberations since the seventh session of the Meeting of the Parties (Minsk, 13-16 June 2017), please see the Committee’s report on its forty-second session. |
1111111111111 | Information on matters considered by the Committee | 11111 | 11 | 11 |
20 April 2011 | Information provided by the Ukrainian NGO regarding the proposed activity in Ukraine (form and supporting information) | ENG ENG |
||
21st session, 20 June 2011 | ||||
ECE/MP.EIA/IC/2011/4 | Report of the twenty-first session of the Implementation Committee | ENG | FRE | RUS |
23 June 2011 | Letter to Ukraine | ENG | ||
22 August 2011 | Reply by Ukraine (received 30.08.11) | ENG | ||
22nd session, 5 - 7 September 2011 | ||||
ECE/MP.EIA/IC/2011/6 | Report of the twenty-second session of the Implementation Committee | ENG | FRE | RUS |
07 September 2011 | Letter to Ukraine | ENG | ||
15 November 2011 | Reply by Ukraine | UKR | ||
23rd session, 5 - 7 December 2011 | ||||
ECE/MP.EIA/IC/2011/8 | Report of the twenty-third session of the Implementation Committee | ENG | FRE | RUS |
25th session, 11 - 13 September 2012 | ||||
ECE/MP.EIA/IC/2012/4 | Report of the twenty-fifth session of the Implementation Committee | ENG | FRE | RUS |
27th session, 12 - 14 March 2013 | ||||
ECE/MP.EIA/IC/2013/2 | Report of the twenty-seventh session of the Implementation Committee | ENG | FRE | RUS |
25 March 2013 | Letter to Ukraine | ENG | ||
30 May 2013 | Reply by Ukraine (received 11.06.13) | ENG | UKR | |
26 August 2013 | Additional information from the NGO | ENG | ||
28th session, 10 - 12 September 2013 | ||||
ECE/MP.EIA/IC/2013/4 | Report of the twenty-eighth session of the Implementation Committee | ENG | FRE | RUS |
Corr.1 | Corr.1 | Corr.1 | ||
12 September 2013 | Letter to Ukraine | ENG Encl.1 Encl. |
||
18 October 2013 | Reply by Ukraine | |||
25 November 2013 | Additional information from Ukraine | ENG Annex |
UKR | |
29th session, 10 - 12 December 2013 | ||||
ECE/MP.EIA/IC/2013/6 | Report of the twenty-ninth session of the Implementation Committee | ENG | FRE | RUS |
6 January 2014 | Letter to Ukraine including the draft findings | ENG Annex |
||
14 February 2014 | Reply by Ukraine (comments to the draft findings) | ENG | UKR | |
30th session, 25 - 27 February 2014 | ||||
ECE/MP.EIA/IC/2014/2 | Report of the thirtieth session of the Implementation Committee | ENG | FRE | RUS |
Meeting of the Parties to the Espoo Convention, 6th session, 2-5 June 2014, Geneva | ||||
Report of the Meeting of the Parties on its sixth session (decision VI/2 on review of compliance) | ENG | FRE | RUS | |
FOLLOW UP TO DECISION VI/2 | ENG | |||
Meeting of the Parties to the Espoo Convention, 7th session, 13-16 June 2017, Minsk | ||||
ECE/MP.EIA/2017/4-ECE/MP.EIA/SEA/2017/4 | Report on the activities of the Implementation Committee to the Meeting of the Parties on its seventh session (see paras 17 - 20) | ENG | FRE | RUS |
Draft decision on the review of compliance with the Convention (paras 29-37) | ENG | |||
ECE/MP.EIA/23 - ECE/MP.EIA/SEA/7 | Report of the Meeting of the Parties to the Convention on its seventh session and of the Meeting of the Parties to the Convention serving as the Meeting of the Parties to the Protocol on its third session (para 27) | ENG | FRE | RUS |
39th session, 5 - 7 September 2017 | ||||
ECE/MP.EIA/IC/2017/4 | Report of the thirty-ninth session of the Implementation Committee (paras 21-25) | ENG | FRE | RUS |
41st session, 13-16 March 2018 | ||||
ECE/MP.EIA/IC/2018/2 | Report of the forty-first session of the Implementation Committee (paras 20-29) | ENG | FRE | RUS |
42nd session, 11-14 September 2018 | ||||
ECE/MP.EIA/IC/2018/4 | Report of the forty-second session of the Implementation Committee (ECE/MP.EIA/IC/2018/4, paras 27-31) Advance copy | ENG |